News | April 1, 2026

Nordex Group Receives 35 MW Order For Wind Farm In The Sauerland Region In Germany

At the end of March, the Nordex Group received an order from STAWAG Energie GmbH, a subsidiary of STAWAG – Stadt- und Städteregionswerke Aachen AG, for five N163/6.X wind turbines. The turbines, with a hub height of 164 meters, are intended for the 35 MW Frettertal wind farm in the municipality of Finnentrop (Olpe district) in the Sauerland region. The contract with this long-standing customer also includes a Premium Service for the turbines over a period of 20 years.

The installation of the N163/6.X turbines is scheduled to begin in summer 2027, with commissioning planned for early 2028.

The topography at the site is characterized by an interplay of deep-cut valleys and ridges. “This favors the use of the N163/6.X turbines with a 164-meter hub height, as the tall towers provide stable wind conditions at rotor height – a decisive factor for high full-load hours,” says Felipe Villalon Waldburg-Zeil, Director Sales Region Central at the Nordex Group. He adds: “We are very pleased about the order from STAWAG. The Frettertal wind farm will specifically strengthen a region in the Sauerland where the expansion of wind energy has so far been relatively modest, but thanks to modern, efficient turbine technology holds great potential.”

Source: The Nordex Group